Planned Maintenance: Electrical Utility Shutdown - ARS R1
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted May 04, 2024 - 15:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 04, 2024 - 07:00 PDT
Scheduled
Purpose:
Replace power pole and tree work. Generation will be provided for buildings H041 and H042. Building H017 panel "B" at the south end of the building will also be generated. All generation tie in will have a half hour of no power at the beginning and end of the shutdown. The solar greenhouse and Pump house/pesticide storage buildings will be affected they have no zone # and will not be generated.

Requested By:
George Jones, UTIL High Voltage
Cell: (530) 681-7318, Task ID: N/A

Impact:
All electrical to the buildings

Affected Buildings:
ARS R1

Affected VLANs:
ACU-1-FW
ANML-RES-SVC-1-FW
ECO-3-NR
HVAC-2-FW

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Apr 25, 2024 - 11:34 PDT
This scheduled maintenance affected: Network, Voicemail, Voice Telephone System, and Wireless.