Planned Maintenance: Campus Data Center Network Downtime

Scheduled Maintenance Report for UC Davis

Completed

The scheduled maintenance has been completed.
Posted Aug 23, 2025 - 16:00 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 23, 2025 - 08:00 PDT

Scheduled

The NOC and Data Center teams will upgrade the layer 2 distribution equipment at the Campus Data Center. Various services will have short downtimes during the maintenance window while they are migrated to new network gear.

The following services will be impacted:

Data Center File Services (Hither Netapp)
DNS 169.237.250.250
F5 load balancers
Backups
IAM backup server
NTP
vpn.ucdavis.edu

The operations phone will also be unavailable.


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Aug 14, 2025 - 08:59 PDT