Planned Maintenance: Data Center Facility
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted May 22, 2020 - 18:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 18, 2020 - 07:00 PDT
Scheduled
Purpose:
Upgrade pre-action fire system in Data Center Machine Room
Requested by: Steven Hamilton, Alarms Foreman

Impact:
Data Center Machine Room Pre-Action System will be disabled during this maintenance (est., 5 days duration). Data Center will have a 24x7 fire watch posted. No impact to services will occur.

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted May 15, 2020 - 14:57 PDT
This scheduled maintenance affected: Data Center Colocation and Network.