Planned Maintenance: Davis Campus Core Network
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted May 14, 2020 - 06:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 14, 2020 - 05:00 PDT
Scheduled
Purpose: Remove old BGP configuration statements from CDF1 and CDF2.

Impact: Risk is moderate due to configuration changes on the core campus routers, CDF1 & CDF2. No impact expected.

Affected:
128.120.0.0/16
169.237.0.0/16
2607:f810::/36


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Apr 30, 2020 - 16:21 PDT
This scheduled maintenance affected: Network.