Network Maintenance: Move network to different ports in Datacenter
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Jun 19, 2018 - 19:31 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 19, 2018 - 18:01 PDT
Scheduled
Purpose:
VLAN ACTG&FINAC-5-FW will be moved from one set of interfaces to another on the Datacenter Colocation router.

Impact:
No loss in connectivity is expected.

Affected:
Directly Affected VLAN:
ACTG&FINAC-5-FW

Indirectly Affected VLANs:
PHYS-PLANT-4-FW
PHYS-PLANT-5-FW
ADMIN-&-RESRC-MGMT-1-FW
HR&RISK-MGMT-6-FW
POLICE-3-FW
CASHIER-1-FW
PHYS-PLANT-6-FW
PHYS-PLANT-1-FW
PHYS-PLANT-2-FW
PHYS-PLANT-3-FW
WASTEWATER-1-FW
ACTG&FINAC-1-FW
ACTG&FINAC-2-FW
ACTG&FINAC-3-FW
ACTG&FINAC-5-FW

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Jun 13, 2018 - 17:55 PDT
This scheduled maintenance affected: Network.