Network Maintenance: Davis Campus Border Network
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Apr 24, 2019 - 21:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 24, 2019 - 18:00 PDT
Scheduled
Purpose:
Configure IPv6 MLD version 2 on the Davis Border Router for the CENIC SVL-HPR and OAK-DC circuits.

Impact:
Risk is moderate due to work on the primary network paths to external sites.
If an issue is discovered during implementation, an outage lasting no more than 20 minutes may be experienced while troubleshooting and/or rollback is performed.

Locations Affected:
128.120.0.0/16
168.150.0.0/17
169.237.0.0/16
2607:f810::/36

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Apr 17, 2019 - 15:28 PDT
This scheduled maintenance affected: Network.