Facilities Planned Electrical Shutdown: Wickson Hall
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Jan 11, 2018 - 07:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 11, 2018 - 05:01 PST
Scheduled
Purpose:
To replace high voltage switch in outer basement. Requested by Derek Fraley, Utilities High Voltage, Cell 681-7316, Reference Task ID # 1438091 – B037.

Impact:
Data connectivity will be lost if UPS batteries are depleted.

Affected:
BUILDINGS:
ENOL
WICKSN


VLANs:
AG-ECONOMICS-2-NR
CHANCELLOR-1-FW
CHANCELLOR-5-FW
DEAN-AG-3-FW
DEAN-AG-5-FW
ENV-STUDIES-1-DMZ
ENV-STUDIES-1-FW
ENV-STUDIES-2
ENV-STUDIES-2-DMZ
ENV-STUDIES-3-DMZ
ENV-STUDIES-3-FW
GEN-ACAD-1
HUMN&COM-DEV-1-FW
HVAC-2-FW
IT-CRETV-3-FW
O&M:UTILITIES-1
PLANT-SCIENCES-1-FW
PLANT-SCIENCES-14-FW
PLANT-SCIENCES-2-FW
PLANT-SCIENCES-3-FW
PLANT-SCIENCES-4-FW
PLANT-SCIENCES-5-FW
PLANT-SCIENCES-9-FW
SAFETY-SVCS-2-FW
VIT&ENOL-1-FW
WLS-UNMANAGED-1
WIRELESS


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Jan 05, 2018 - 14:36 PST
This scheduled maintenance affected: Network.