Planned Maintenance: Campus Data Center Generator Test
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Dec 17, 2024 - 07:30 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 17, 2024 - 05:30 PST
Scheduled
Purpose:
Facilities will perform an operational test of the Campus Data Center's Generator and automatic fail-over equipment as part of this maintenance. During this test, the Campus Data Center will briefly switch to the electrical power supplied by the building generator. This semi-annual test is part of our established maintenance schedule.

Impact:
High Performance Computing servers and other co-location equipment that are not on UPS and hosted within the Campus Data Center, will lose power during the test.
Otherwise, the Campus Data Center UPS systems will carry the load during the transitions; Therefore, no impact to other services is expected.

Affected Services:
High Performance Computing servers and other co-location equipment hosted within the Campus Data Center, and not on UPS, will be affected.
In the event of a UPS failure, other services that are hosted in the Campus Data Center may be disrupted.
Posted Dec 12, 2024 - 08:35 PST
This scheduled maintenance affected: Data Center Colocation and Network.