Planned Maintenance - Electrical Utility Shutdown - Fire & Police Building

Scheduled Maintenance Report for UC Davis

Completed

The scheduled maintenance has been completed.
Posted Feb 20, 2025 - 05:15 PST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 20, 2025 - 05:00 PST

Scheduled

Purpose:
To add breakers into the main switch board for the new HVAC equipment on the rooftop.

Impact:
Potential impact to network

Affected Buildings:
FIRE&POLICE

Affected VLANs:
ARM-ALARMS-1-FW
ARM-ALARMS-1-NR
DOE-1-FW
FIRE-DEPT-1-FW
FIRE-DEPT-2-FW
PD-AUDIO-1-DMZ
PD-VIDEO-1-FW
PD-VIDEO-1-NR
PHYS-PLANT-2-FW
POLICE-4-FW
POLICE-911-DMZ
POWER-1-NR
SET-TOP-BOX-1
SHRD-SVC-CTR-1-FW
WIRELESS

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Feb 19, 2025 - 17:36 PST
This scheduled maintenance affected: Network, Voicemail, Voice Telephone System, and Wireless.