Planned Maintenance - Electrical Utility Shutdown - TB 196
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Dec 11, 2024 - 12:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 11, 2024 - 08:00 PST
Scheduled
Purpose:
Re-Sag Power Lines

Impact:
All electrical to the buildings

Affected Buildings:
TB 196

Affected VLANs:
CNPRC-5-NR
ECO-3-NR
POWER-1-NR
PRIM-RES-CTR-1-FW
PRIM-RES-CTR-3-FW
PRIM-RES-CTR-4-FW
WIRELESS

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Dec 09, 2024 - 13:06 PST
This scheduled maintenance affected: Network, Voicemail, Voice Telephone System, and Wireless.