Planned Maintenance: Campus Data Center Generator Test
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Oct 07, 2016 - 07:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 07, 2016 - 05:45 PDT
Scheduled
Purpose:
Facilities will test the Campus Data Center backup-power generator and automatic power-transfer system to ensure the system is functional and prepared for an actual utility power-outage. This semi-annual test occurs on the first Friday of April and October, and is part of an established maintenance schedule.

Impact:
Any High Performance Computing servers or other co-location equipment which are not served by a UPS and hosted in the Data Center, will lose power during the test. No impact to other services is expected.

Affected Services:
The affected equipment will be High Performance Computing servers, or other co-location equipment, which are not on a UPS. Other services hosted in the Campus Data Center may be affected if a UPS failure occurs.

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Oct 03, 2016 - 08:51 PDT
This scheduled maintenance affected: Data Center Colocation.