Network Maintenance: Installing additional UPS and extra battery pack for NOC servers
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Sep 26, 2017 - 07:30 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 26, 2017 - 06:00 PDT
Scheduled
Purpose:
Installing additional UPS and an extra UPS battery pack for an existing UPS.

Impact:
None is expected, as the switches attached to them are dually powered to different circuits.

Locations Affected:
BUILDINGS:
TELCOM

VLANs:
NOC-1-FW
NOC-3-NR

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Sep 22, 2017 - 15:40 PDT
This scheduled maintenance affected: Network.