Electrical Utility Maintenance: Q-Zones
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Mar 21, 2020 - 17:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 21, 2020 - 07:00 PDT
Scheduled
Purpose:
To replace a power pole
Requested by George Jones, Utilities High Voltage,
Cell 530-68-7318, Reference Task # 1809064 – Q-Zones

Impact:
Network connections will be lost as UPS run out of power.

Locations Affected:
BUILDINGS:
FPS Facility (Main Lab & Office)/ Q074
Germplasm Laboratory/ Q053
Viticulture Relocation A/ Q047


VLANs:
FPMS-1-FW
HVAC-2-FW
PLANT-PATH-1-FW
USDA-2-FW
USDA-3-DMZ
USDA-3-FW
VIT&ENOL-1-FW


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Mar 17, 2020 - 16:10 PDT
This scheduled maintenance affected: Network, Voicemail, Voice Telephone System, and Wireless.