Facilities Planned Electrical Shutdown: Freeborn Hall
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Feb 17, 2018 - 12:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 17, 2018 - 06:00 PST
Scheduled
Purpose:
Contractor to replace high voltage switch. Requested by Derek Fraley, BMS High Voltage Shop, Cell 681-7316, Reference Task ID #1483408 – B Zones.

Impact:
Data connectivity will be lost once UPS batteries are depleted.

Affected:
BUILDINGS:
FREEBORN

VLANs:
ASUCD-1-FW
BOOKSTORE-1-FW
BOOKSTORE-2
CAMPUS-EV&IN-1-FW
CRU-PCI-1
HVAC-2-FW
INTRCOL-ATHL-3-FW
MU-GENERAL-1
MU-GENERAL-2
MU-GENERAL-3
REC-HALL-2-FW
REC-HALL-3
VC-STU-AFFRS-3-FW
WIRELESS


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Feb 14, 2018 - 10:49 PST
This scheduled maintenance affected: Network.