Network Maintenance: Datacenter colocation network move
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Feb 08, 2018 - 06:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 08, 2018 - 04:00 PST
Scheduled
Purpose:
Move Datacenter collocation clients to new networking equipment.

Impact:
Connections will experience outages as they are moved to new equipment. In the case of multiple connections on the same VLAN, longer outages may be experienced to prevent the possibility of bridge loops.

Affected:
CHANCELLOR-11-12-DMZ
CHANCELLOR-11-FW
CHANCELLOR-12-FW
DC-CLIENT-SVC-12-DMZ
DC&CLIENT-SVC-12-FW
DC&CLIENT-SVC-54-FW
DEAN-AG-6-FW
DEAN-MED-ADM-13-FW
DEAN-MED-ADM-5-FW
EDUCATION-1-DMZ
EDUCATION-1-FW
EDUCATION-2-FW
GRAD-STUDIES-1-2-DMZ
GRAD-STUDIES-1-FW
GRAD-STUDIES-2-FW
IET-EAIS-SANDBOX-1-FW
MCCLELLAN-NRC-1-DMZ
MCCLELLAN-NRC-1-FW
M-CURIC-SUPT-1-DMZ
MGMT-SCH-OF-1-DMZ
MGMT-SCH-OF-1-FW
MGMT-SCH-OF-2-FW
MONDAVI-1-FW
OCM-1-FW
O&M:UTILITIES-1
O&M:UTILITIES-2
O-M:UTILITIES-DMZ
PLANT-PATH-4
STUDENT-AFFRS-1-FW
STUDENT-AFFRS-3-FW
STUDENT-AFFRS-8-NR
U-EXTENSION-3-FW
UTILITIES-1-VPN
WATER-1-NR

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Feb 06, 2018 - 09:25 PST
This scheduled maintenance affected: Network.