PLANNED MAINTENANCE: Campus Data Center Generator Test
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Oct 02, 2020 - 07:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 02, 2020 - 05:45 PDT
Scheduled
Purpose:
Facilities will test the Campus Data Center's fail-over equipment as part of this maintenance. The Campus Data Center will be switched, briefly, to the power supplied by the generator. This semi-annual test, which occurs on the first Fridays of April and October, is part of an established maintenance schedule.

Impact:
High Performance Computing servers and other co-location equipment which are not on UPS and hosted within the Campus Data Center, will lose power during the test. No impact to other services is expected. The Campus Data Center UPS systems will carry the load during the transition to the generator.

Affected Services:
High Performance Computing servers and other co-location equipment hosted within the Campus Data Center, and not on UPS, will be affected. In the event of a UPS failure, other services which are hosted in the Campus Data Center may be disrupted.


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Sep 25, 2020 - 15:47 PDT
This scheduled maintenance affected: Data Center Colocation, Network, and Virtualization.