Electrical/Utility Maintenance: Haring Hall / D042
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Jun 30, 2020 - 14:30 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 30, 2020 - 06:01 PDT
Scheduled
Purpose:
To cutover electrical feeders from Transformer C.

Impact:
This shutdown will affect all electrical power to the east wing of Haring Hall. Generated power will be provided for the first floor freezers.

Requested by Ryan Burgess, Utilities High Voltage,
Cell 530-304-3184, Reference Task #1832114 – D042

Locations Affected:
BUILDINGS:
HARING

VLANs:
ACAD-PREP-PROG-1-FW
ARCH-&-ENGR-2
GEN-ACAD-1
IT-CRETV-3-FW
O&M:UTILITIES-1
VM-MED&EPIDM-2-FW
VM-RESEARCH-1-FW
WIRELESS

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Jun 22, 2020 - 15:57 PDT
This scheduled maintenance affected: Network, Voice Telephone System, and Wireless.