Planned Maintenance: Electrical Shutdown - Annual Fund, TBs 206, 207, Temporary Classrooms 1, 2 & 3
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Feb 23, 2019 - 11:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 23, 2019 - 07:00 PST
Scheduled
Purpose:
To repair a breaker and install electric meters.
Requested by Nick Harden, Utilities High Voltage,
Cell 530-219-6928 Reference Task ID # 1139162- E Zones

Impact:
This shutdown will affect all electrical power to the buildings.

Affected:

BUILDINGS:
ANNUAL FUND TRAILER
TB 206
TB 207
TEMPORARY CLASSROOM 1
TEMPORARY CLASSROOM 2
TEMPORARY CLASSROOM 3

VLANs:
ALUMNI-AFFRS-1-FW
COE-ITSS-10-FW
DC&CLIENT-SVC-12-FW
DEAN-AG-3-FW
DEAN-AG-6-DMZ
ECO-3-NR
EDUCATION-1-FW
EDUCATION-2-FW
ENG-ELEC&CMP-1
ENG-ELEC&CMP-2
ENG-ELEC&CMP-3
ENG-MCH&AERO-4
GEN-ACAD-1
GEN-ACAD-2-FW
IT-COMMUNRES-13-FW
IT-CRETV-3-FW
WIRELESS

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Feb 19, 2019 - 10:43 PST
This scheduled maintenance affected: Network and Wireless.