Scheduled
Purpose:
UCDH is finishing their migration to a new ONS. This could include some diagnostics, fixes for links that did not come up, and fail-over testing to confirm functionality of the new system.

Impact:
There should be no outage as the system will be migrated in a way that would not take down both of our links at once. We have two links to Quest Datacenter for resilience. In the past, one of two links provides enough bandwidth to maintain regular traffic levels.

Location Affected:
Quest Datacenter


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Jan 15, 2020 - 16:08 PST