Network Maintenance: Jungerman Hall (Crocker Lab) / E010 Pre-Approved Electrical Utility Shutdown
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Jan 05, 2021 - 12:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 05, 2021 - 08:00 PST
Scheduled
Purpose:
Pre-Approved Electrical Utility Shutdown- To allow metering department to access transformers and make repairs.

Impact:
BUILDINGS:
JUNGERMAN

Locations Affected:
VLANs:
AQRC-2-FW
CROC-NUC-LAB-1
CROC-NUC-LAB-2
CYCLOTRON-1-FW
HVAC-2-FW
POWER-1-NR


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Dec 18, 2020 - 10:28 PST
This scheduled maintenance affected: Network and Wireless.