Planned Maintenance: Enology Laboratory Building / B036 : Electrical Utility Shutdown
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted May 21, 2020 - 11:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 21, 2020 - 08:01 PDT
Scheduled
Purpose: To install new feeder, remove old breakers, and install direct lug connections.

Impact: This shutdown will affect all electrical equipment and network throughout the entire building.

Affected:

BUILDINGS:
ENOLOGY LABORATORY BUILDING

VLANs:
VIT&ENOL-1-FW


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted May 20, 2020 - 12:10 PDT