Facilities Planned Electrical Shutdown: ARC
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted 10 months ago. Jan 05, 2018 - 05:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 10 months ago. Jan 05, 2018 - 03:00 PST
Scheduled
Purpose:
To install new breaker in main MSB. Requested by Justin Wisterman, 4G11, BMS Electrical Shop, Cell 400-0692, Reference Task ID # 1520776 – C034.

Impact:
Data connectivity will be lost is UPS batteries are depleted.

Affected:
BUILDINGS:
Activities & Recreation Center
Activities & Recreation Center Pavilion
Baseball Pressbox

VLANs:
ARCH-&-ENGR-2
BOOKSTORE-1-FW
BOOKSTORE-2
GEN-ACAD-1
GEN-ACAD-2-FW
HOUSING-10-FW
HOUSING-7-FW
HOUSING-9-NR
HVAC-2-FW
INTRCOL-ATHL-1-FW
INTRCOL-ATHL-2
INTRCOL-ATHL-3-FW
IT-CRETV-3-FW
MU-GENERAL-1
MU-GENERAL-2
POWER-1-NR
REC-HALL-1
REC-HALL-2-DMZ
REC-HALL-2-FW
REC-HALL-3
REC-HALL-4
WIRELESS

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted 10 months ago. Jan 03, 2018 - 10:43 PST
This scheduled maintenance affected: Network.