Facilities Planned Electrical Shutdown: Silo South
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Feb 28, 2017 - 09:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 28, 2017 - 05:00 PST
Scheduled
Purpose:
To assist contractor with installing breakers and feeders for new construction. Requested by Gerry Ownby, 4G18, BMS Electrical Shop. Cell 530-979-1567 Reference Task # 1343478 – E164

Impact:
Data connectivity will be lost once UPS batteries are depleted.

Affected:
BUILDINGS:
SILO SOUTH

VLANs:
BOOKSTORE-1-FW
FOOD-SERVICE-1-FW
HVAC-2-FW
INTRN&CR-CTR-1-FW
WIRELESS
MU-GENERAL-1
REC-HALL-2-FW
STUDENT-AFFRS-1-FW
WLS-UNMANAGED-1

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Feb 24, 2017 - 16:10 PST
This scheduled maintenance affected: Network.