Electrical Shutdown: Dutton Hall
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Apr 17, 2015 - 06:30 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 17, 2015 - 05:30 PDT
Scheduled
Purpose:
To change breakers in panel L.. Requested by Rick Noring, Utilities High Voltage, Cell 681-2061 Reference job # 2558649–B074.

Impact:
Data connectivity will be lost if UPS batteries are depleted.

Building:
DUTTON HALL

VLANs:
ACAD-PREP-PROG-1-DMZ
ACAD-PREP-PROG-1-FW
ACTG&FINAC-1-FW
CASHIER-1-FW
COUNSELING-2-NR
FIN-AID&EMPL-1-FW
FIN-AID&EMPL-2
HVAC-2-FW
INTRCOL-ATHL-1-FW
INTRCOL-ATHL-3-FW
LIGHTING-1-NR
LIGHTING-2-NR
MOOBILENET(X)
O&M:UTILITIES-1
REGISTRAR-1-FW
STDT-JUD-AFF-1-FW
STUDENT-AFFRS-1-FW
STUDENT-AFFRS-3-FW


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Apr 15, 2015 - 10:14 PDT
This scheduled maintenance affected: Network.