Facilities Planned Electrical Shutdown: Kemper Hall
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Dec 02, 2016 - 13:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 02, 2016 - 07:00 PST
Scheduled
Purpose:
Electrical Panels 1R7, 1R13 & 1R20. This will affect all electrical to rooms 1104, 1105, 1139, 1142, 1145, 1150, 1151 and 1152. To tie in new conduits in panels. Requested by Justin Wisterman, 4G11, BMS Electric Shop, Cell 400-0692, Reference Task ID# 1066652 – E157.

Impact:
Data connectivity originating from the Kemper 1.2 will be lost once UPS batteries are depleted.

Affected:
BUILDINGS:
KEMPER 1.2

VLANs:
COE-ITSS-8-FW
DEAN-ENGIN-1
DEAN-ENGIN-4
ENG-CHEM&MAT-1
ENG-CHEM&MAT-2-FW
ENG-CHEM&MAT-3-FW
ENG-CMPR-SCI-7
ENG-CMPR-SCI-8
ENG-ELEC&CMP-1
ENG-ELEC&CMP-2
ENG-ELEC&CMP-3
ENG-MCH&AERO-1
ENG-MCH&AERO-4
WIRELESS

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Nov 30, 2016 - 13:03 PST
This scheduled maintenance affected: Network.