Facilities Planned Electrical Shutdown: Bike Barn & South Silo
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Apr 15, 2017 - 09:30 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 15, 2017 - 05:30 PDT
Scheduled
Purpose:
To install “CT”’s to meter power usage. Requested by Fabian Ceja, Utilities High Voltage, Cell 681-8588 Reference Task # 1244050 – E164 – E002.

Impact:
Data connectivity will be lost if UPS batteries are depleted.

Affected:
BUILDINGS:
SILO SOUTH
TB 24 (BIKE BARN)

VLANs:
ASUCD-1-FW
BOOKSTORE-1-FW
FOOD-SERVICE-1-FW
HVAC-2-FW
INTRN&CR-CTR-1-FW
WIRELESS
MU-GENERAL-1
REC-HALL-2-FW
STUDENT-AFFRS-1-FW
WLS-UNMANAGED-1


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Apr 12, 2017 - 13:38 PDT
This scheduled maintenance affected: Network.