Scheduled
Purpose:
To change multiple breakers. Requested by Kevin Eubanks, 4G72, BMS Electric Shop,
Cell 530-979-7050, Reference Task ID# 1379253 – C098

Impact:
Data connectivity will be lost if UPS batteries are depleted.

Affected:
BUILDING:
CHEMISTRY

VLANs:
CHEMISTRY-1-FW
CHEMISTRY-2-FW
CHEMISTRY-3-FW
GEN-ACAD-1
HVAC-2-FW
WIRELESS
O&M:UTILITIES-1


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Mar 27, 2017 - 15:07 PDT