Facilities Planned Electrical Shutdown: Vet Med 2
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Nov 18, 2015 - 07:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 18, 2015 - 05:01 PST
Scheduled
Purpose:
This will affect all electrical, outlets and equipment with 120 volt & 240 volt power to rooms. To repair main breaker. Requested by Gerry Ownby, 4G18, BMS Electrical Shop, 4G18. Cell 979-1567, Reference job # 2628749 – G052.

Impact:
Data connectivity will be lost once UPS batteries are depleted.

Affected:
BUILDINGS:
VET MED 2

VLANs:
CTR-CPANHLTH-1-FW
CTR-CPANHLTH-2-FW
HVAC-2-FW
MOOBILENET(X)
VH-ADMIN-1-FW
VH-ADMIN-2-FW
VH-ADMIN-4
VM-GEN-I&R-1-FW
VM-RESEARCH-1-FW
WLS-UNMANAGED-1


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Oct 29, 2015 - 14:51 PDT
This scheduled maintenance affected: Network.