Facilities Planned Electrical Shutdown: Bainer Hall 1st Floor
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Aug 07, 2017 - 15:30 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 07, 2017 - 07:00 PDT
Scheduled
Purpose:
To install new breakers and feeder wire for remodel. Requested by Gerry Ownby, 4G18, BMS Electrical Shop, Cell 530-979-1567, Reference Task ID # 1475501 – E009.

Impact:
Data connectivity from 1.3 will be lost once UPS batteries are depleted.

Affected:
BUILDINGS:
BAINER 1.3

VLANs:
ENG-BIO&AG-1
ENG-CHEM&MAT-2-FW
ENG-CHEM&MAT-3-FW
ENG-CIVL&ENV-1
ENG-CIVL&ENV-4
ENG-MCH&AERO-4
WIRELESS


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Aug 04, 2017 - 11:05 PDT
This scheduled maintenance affected: Network.