Facilities Planned Electrical Shutdown: Ghausi Hall
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Jan 30, 2016 - 16:30 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 30, 2016 - 07:00 PST
Scheduled
Purpose:
This will affect all electrical powered systems, including lights, pumps, motors, actuators, fume hoods, air handler (heating, cooling, ventilation). This is for work that is being done in room 1104. The emergency power for the building will still be available during this time. To swap power feeder at the main distribution to accommodate the above listed room. Requested by Brad Gaby, 4G50, BMS Electric Shop, Cell 979-1864 Reference job #2640745EL2 – E169

Impact:
Data connectivity will be lost once UPS batteries are depleted.

Affected:
BUILDINGS:
GHAUSI

VLANs:
COE-ITSS-1-NR
COE-ITSS-2-FW
COE-ITSS-3-FW
ENG-AP-SCI-1
ENG-AP-SCI-4
ENG-BIOMED-2
ENG-CHEM&MAT-1
ENG-CHEM&MAT-2-FW
ENG-CIVL&ENV-1
ENG-CIVL&ENV-2
ENG-CIVL&ENV-4
ENG-CIVL&ENV-6-DMZ
ENG-CIVL&ENV-6-FW
ENG-ELEC&CMP-2
HVAC-2-FW
IT-CRETV-3-FW
LIGHTING-1-NR
LIGHTING-2-NR
MOOBILENET(X)



----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Jan 27, 2016 - 15:49 PST
This scheduled maintenance affected: Network.