Facilities Planned Electrical Shutdown: ARS S1
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted May 20, 2016 - 18:30 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 20, 2016 - 18:00 PDT
Scheduled
Purpose:
This will affect all electrical power to the entire building. To install breaker. Requested by Russ Korupp, BMS Electrical Shop, cell 681-2059 Reference job #2644141EL1 – H284.

Impact:
Data connectivity will be lost if UPS batteries are depleted.

Affected:
Building:
ARS S-1

VLANs:
WIRELESS-DESKTOP
VH-ADMIN-1-FW
VM-RESEARCH-1-FW


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted May 20, 2016 - 16:09 PDT
This scheduled maintenance affected: Network.