Electrical Shutdown: Bainer Hall Room 1202
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Dec 24, 2014 - 09:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 24, 2014 - 08:00 PST
Scheduled
Purpose:
To install breaker. Requested by Marvin Leblanc, BMS Electric Shop, cell 979-1537 Reference job # 2532426 - E009.

Impact:
Data connectivity will be lost once UPS batteries are depleted.

Buildings:
BAINER

VLANs:
ENG-BIO&AG-1
ENG-CHEM&MAT-1
ENG-CIVL&ENV-4
ENG-MCH&AERO-4

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Dec 19, 2014 - 14:35 PST
This scheduled maintenance affected: Network.