Facilities Planned Electrical Shutdown: Meyer 4th Floor NE
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted May 25, 2017 - 07:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 25, 2017 - 05:00 PDT
Scheduled
Purpose:
Sub panel tie in for room 4427. Requested by Brad Gaby, BMS Electrical Shop, Cell 979-1864, Reference Task ID# 1268691– E139.

Impact:
Data connectivity will be lost if UPS batteries are depleted.

Affected:
TUPPER HALL 4.2, ROOM 4414

VLANS:
WIRELESS
ENV-TOX-1-FW


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted May 19, 2017 - 12:24 PDT
This scheduled maintenance affected: Network.