Facilities Planned Electrical Shutdown: N Zones
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Sep 20, 2017 - 09:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 20, 2017 - 05:01 PDT
Scheduled
Purpose:
To install generator conductors. Requested by Bryant Pitner, 4G88, BMS Utilities, Cell 530-574-5373, Reference Task #1484550 - N Zones.

Impact:
Data connectivity will be lost if UPS batteries are depleted.

Affected:
BUILDINGS:
HEAD HOUSE 51
VEG CROPS HQ B

VLANs:
WIRELESS
PLANT-SCIENCES-1-FW
PLANT-SCIENCES-2-FW
PLANT-SCIENCES-3-FW
PLANT-SCIENCES-9-FW


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Sep 18, 2017 - 12:55 PDT
This scheduled maintenance affected: Network.