Facilities Planned Electrical Shutdown: Silo South, TB 24 (Bike Barn)
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Aug 30, 2016 - 07:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 30, 2016 - 06:01 PDT
Scheduled
Purpose:
This will affect ALL electrical power to both buildings. To install breaker. Requested by George Jones, Utilities High Voltage, cell 681 - 7318. Reference job # 1087418 – E001 – E164

Impact:
Data connectivity will be lost if UPS batteries are depleted.

Affected:
BUILDINGS:
SILO SOUTH
TB 24 (BIKE BARN)

VLANs:
ASUCD-1-FW
FOOD-SERVICE-1-FW
HVAC-2-FW
WIRELESS
REC-HALL-2-FW
STUDENT-AFFRS-1-FW
WLS-UNMANAGED-1


----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Aug 23, 2016 - 11:09 PDT
This scheduled maintenance affected: Network.