Planned Maintenance: Electrical Shutdown P & Q Areas
Scheduled Maintenance Report for UC Davis
Completed
The scheduled maintenance has been completed.
Posted Oct 10, 2015 - 15:30 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 10, 2015 - 08:00 PDT
Scheduled
Purpose:
To replace power pole. Requested by George Jones, Utilities High Voltage, cell 681-7318. Reference job # 2521635HV1 – P & Q Zones

Impact:
This will affect all electrical services in the the P & Q areas. Data connectivity will be lost once UPS batteries are depleted.

Affected:
BUILDINGS:
BEE BIOLOGY
HEADHOUSE 2 & 3

VLANs:
ENTOMOLOGY-1-FW
ENTOMOLOGY-2

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted Oct 01, 2015 - 13:03 PDT
This scheduled maintenance affected: Network.