Planned Maintenance: Data Center Firewall
Scheduled Maintenance Report for UC Davis
Completed
The firewall maintenance was completed without incident. The service is again in high availability failover. Further maintenance will be scheduled to continue upgrading the firmware.
Posted 12 days ago. Aug 12, 2017 - 11:26 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 12 days ago. Aug 12, 2017 - 11:00 PDT
Scheduled
Purpose:
This downtime is to install new firmware on both Data Center firewalls located at Quest to address known issues that caused two recent outages. The firewalls are highly available with redundant hardware. We don’t anticipate any downtime. If downtime is necessary, it will be for reboots of the firewalls. This will cause a short outage, approximately 15 minutes, during that maintenance window.

Impact:
All IET managed services, as well as banner and KFS, will be impacted during a firewall reboot. Campus colocation clients utilizing physical colocation or the Data Center Private Cloud Services will not be affected.

----------------------------
IT Express Service Desk
ithelp@ucdavis.edu
530.754.HELP (4357)
Posted 15 days ago. Aug 08, 2017 - 15:47 PDT
This scheduled maintenance affected: Banner, Box, Canvas, CAS, Computing Accounts, Crashplan Backup Service, Data Center Colocation, DavisMail, DHCP, DNS, Duo Multifactor Authentication, Email Lists, Email Routing, FGS, Geckomail, IAM, Kerberos, KFS, Kuali Rice, LDAP, MyInfoVault, MyUCDavis Employee, myUCDavis, Network, Network Time, Qualtrics, SAN & DCFS, ServiceNow, Shibboleth, SiteFarm, Smartsite, Software Website, TRS, uConnect DS, uConnect Cloud, uConnect eFax, uConnect Lync, uConnect On-Premise, Virtualization, Web CMS, Web Hosting, and Wireless.